Continue Straight to State Route 42 North
Future
in NC
Jump to Photos (New Link 5/8/22)
Interstate 42 is a 137 mile planned interstate route from I-40 south of Raleigh to Morehead City mostly along existing US 70. AASHTO gave approval to the number in May 2016, though originally NCDOT asked that the route be designated I-36, after the corridor was granted interstate status under the 2015 Fixing America's Surface Transportation (FAST) Highway Act. The first two segments of I-42, the Clayton and Goldsboro Bypasses, should be signed in 2022. Here's the corridor map as submitted in its AASHTO application:1
This page will summarize the progress in building and signing the route from west to east. While two segments will receive I-42 signage in 2022, the projected completion date for the entire route is 2032.2 I've broken the route into 8 segments with a description of the progress of constructing I-42 in each. As of May 2022, 2 Segments are Complete:
Segment 1 (Updated 6/23/22)
US 70 Clayton Bypass
Road Type: Interstate Standard Freeway Length: 10.0 Miles
Status: Complete [Except for I-42 Signage]
This segment could be signed as I-42 today as it is Interstate standard. NCDOT got approval from AASHTO at its Fall 2021 meeting for it to be signed as I-42 from I-40 to US 70 Business, conditioned on FHWA approval. The FHWA granted its approval in March 2022. According to a press release by NCDOT a timeline for the signing of I-42 is to be released later in 2022.3 NCDOT announced on June 23, 2022 that the ramp from US 70 to I-40 East would permanently close on July 6 as part of the NC 540 Extension 'Turbine Interchange' project. Unknown if this will effect the timeline of signing the Bypass as I-42. Photos from this segment are in the Photos section below.
Drive this Segment watching two New Videos from RoadwayWiz from Summer 2021: Eastbound Westbound
Segment 2 (Updated 5/8/22)
US 70 from End of Clayton Bypass to Beginning of US 70 Goldsboro Bypass (includes Bypass US 70 in Smithfield)
Road Type: 4-lane Divided Roadway with some Freeway Sections Length: 22.5 Miles
Status: Needs Upgrade to Interstate Status
There are two funded projects and one feasibility study underway to upgrade this section of US 70:
The first will upgrade 5 miles of US 70 to Interstate Standards from US 70 Business to the Neuse River Bridge (W-5600) , NCDOT will replace the current US 70 intersections with Wilson Mills Road and Swift Creek Road with interchanges starting in the spring of 2021. Originally the plan was to award the contract in September 2020, however, due to COVID funding issues, the contract letting was postponed until March 2021 but work started on May 12. As of April 15, 2022 the project is more than 1/4 done, at 26.9% complete.4 The plan is to have US 70 be carried on a bridge over Wilson Mills Road while a bridge will carry Swift Creek Road over US 70. A connector road paralleling US 70 between the two roads will also be built. The total cost for the Wilson Mills interchanges is estimated at $77 million and the project is to be completed by the middle of March 2025.5
Here's a map of the project area:6
NCDOT advertised the W-5600 contract on January 16, 2021. Among the sign plans included those for the new exit signs for Swift Creek and Wilson Mills Road, along with the new signs for the Business 70 exit westbound:7
The second project will upgrade US 70 to Interstate Standards in Princeton Area (R-5829AB) from US 70A to Goldsboro Bypass Design Build Projects. Project A to start in 2025, Project B in 2028.*
Here's a map of the project area:8
A Feasibility Study (FS-1604A) was published in August 2018 for determining how to upgrade the remaining section between the Neuse River Bridge and Smithfield. It split the segment into 4 sections and compared the cost of simply upgrading shoulders to a complete upgrade to interstate standards of the existing route. The upgrade option was the preferred alternative, though they suggested maybe simply upgrading shoulders could get the route signed as I-42 for Sections 1 and 2, that is from the end of the Clayton Bypass to Creech's Mill Road in Smithfield (includes I-95 interchange) . Here's a Link to the Report. Construction Date TBD. Here's a map of the study area:9
There are also several pavement upgrade projects for US 70 in Johnston County which may be part of I-42, depending on what final alignment is chosen, including a project C204333 (TIP No. I-6044) that will, as part of the project, reconstruct US 70 Bypass and other portions of US 70. Here is a map of the project area and 2 of the 4 work zones, work started in August 2019 and was scheduled to be completed in October 2020, the project no longer appeared on NCDOT's Construction Progress Report website as of November 2020:10
Here's the typical section plan showing shoulders varying from 2 to 10 feet. Rumble strips will also be added to Bypass 70 section, the only section that is currently a freeway:11
Segment 3 (Updated 3/16/22)
US 70 Goldsboro Bypass and US 70 to NC 903 in LaGrange
Road Type: Interstate Standard Freeway Length: 21.6 Miles
Status: Complete [Except for I-42 Signage, expected in 2022]
According to Jim Dunlop, a NCDOT sign engineer, an application was sent to AASHTO in the fall of 2021 regarding signing the Goldsboro Bypass as I-42.12 On February 13, 2022 the applications were finally posted on the AASHTO Special Committee on US Route Numbering website.13 The application for the Goldsboro Bypass was approved, along with the Clayton Bypass (Segment 1), pending approval also by the FHWA. Despite a Super 70 Commission Director reporting in his January/February 2019 message that the FHWA has approved signing the Goldsboro Bypass as I-42,14 NCDOT engineer Dunlop indicated they had not done so as of the summer of 2021. It was announced again by the Super 70/I-42 Group at a meeting on March 16, 2022. This time NCDOT issued a press release indicating the approval of both the Goldsboro and Clayton Bypasses as I-42.1 The press release indicated a timetable for the placement of I-42 signs would be released later in the year. There are no current projects listed at either the state or division level related to I-42 signage. There was some conjecture that NCDOT would apply to AASHTO at their Fall 2019 meeting to decommission Bypass US 70 on the Goldsboro Bypass and ask that it be replaced by I-42, however that didn't happen. A future request would reduce the amount of sign changes that would be needed.
Link to video Driving the Goldsboro Bypass along US 70 Bypass West
Segment 4 (Updated 6/23/22)
Existing US 70 from NC 903 in LaGrange to the to be built Kinston 'Shallow' Bypass and along an upgraded US 70 to Dover
Road Type: Upgrade to Interstate Freeway (part to be built on new location) Length: 21.1 Miles
Status: Construction was to start in 2020 (US 70 Freeway) and 2027 (Bypass), however due to COVID-19 related budget shortfalls, the projects now do not have an official start date, most likely not until after 2029.
New-In June 2022 NCDOT posted a press release indicating a new website had been created to provide a '3D view' of the Kinston Bypass, though the construction date has yet to be announced (see below). You can use the website to take a Virtual Tour of the Bypass.
In April 2018, NCDOT announced 12 possible alternative routes for the Kinston Bypass Project (R-2553) that will run from the end of the US 70 Goldsboro Bypass near LaGrange to the beginning of the US 70 freeway in Dover. Here was a map of the possible alternatives:15
NCDOT held a public hearing in Kinston on August 31, 2019 allowing the public to weigh in on the possible routings. Many Lenoir County businesses and officials supported the 'Shallow Bypass' or Alternative 1SB which would have the Bypass follow existing US 70 for 14.6 of the 21.1 miles in this segment, the remainder would be on a new 6.5 mile bypass close to the existing US 70 and its businesses. NCDOT selected this as the Preferred Alternative in 2020.
Here's a map of the chosen alternative:
The pre-COVID timeline for the project was for right-of-way acquisition to start in 2023, presuming the environmental impact statement was approved in 2021. Construction would then have started in 2027. This has now been changed, the Final EIS is to be released in the winter of 2022, right-of-way acquisition now will start in 2026 with the construction date still to be determined. The western section of the bypass follows current U.S. 70 for approximately 7 miles to just east of NC 148 (CF Harvey Parkway). Interchanges would be located at Willie Measley/Jim Sutton roads, Albert Sugg/Barwick Station roads, and NC 148. A new interchange east of NC 148 would provide access to the new shallow bypass section, which would be parallel existing U.S. 70 to the south for approximately 6.5 miles. Interchanges along the Bypass would be located at NC 11/NC 55, US 258 (South Queen Street), and at NC 58 (Trenton Highway). A new interchange east of Lenoir Community College would connect the shallow bypass back to existing U.S. 70. The bypass would then follow existing U.S. 70 to the end of the project near Dover, upgrading US 70 to a freeway with interchanges at Wyse Fork /Caswell Station Roads and Old U.S. 70 (West Kornegay Street) in Dover.16 Meanwhile, a project that will resurface and upgrade 3.1 miles of the existing US 70 freeway to Interstate Standards from the Bear Creek Bridge at the end of the Goldsboro Bypass to Willie Measley Road east of LaGrange (Project I-6034) was to be let in September 2019, but in July 2019 that was pushed back to March 2020, the project then disappeared from the March 2020 Letting list in February, also a COVID related postponement.
Visit NCDOT's Kinston Bypass Project website.
Segment 5 (Updated 8/2/21)
US 70 Freeway from Dover to New Bern
Road Type: Freeway Length: 26.1 Miles
Status: Needed Upgrade to Interstate Status, Complete of as March 2021 [Except for I-42 Signage]
NCDOT awarded a contract in the Spring of 2019 to repave and widen US 70 to interstate standards along the existing freeway between Dover and the Neuse River Bridge in New Bern. Work was completed in the spring of 2021. July 2020 Google Maps Street View images show that all of the US 70 shoulder work has been completed, work is now proceeding on upgrading exit and entrance ramps, the last to be completed were in the New Bern area.
Here's a map of the project location:17
Signing of the section as I-42 cannot occur until the Kinston Bypass and related construction to the east are completed.
See the completion of shoulder widening in Photos section below.
Segment 6 (Updated 6/23/22)
US 70 Neuse River Bridge to Havelock Bypass
Road Type: 4-lane Divided Roadway Length: 13.7 Miles
Status: Needs Upgrade/New Construction to Interstate Freeway
A 2-Part Project: First is from Neuse River Bridge to Thurman Road, (U-5713/R-5777AB, 5.1 Miles). Start of Construction-2019 Completion estimated in December 2023 (Design/Build Project was awarded in September 2019 and work started on October 22.18 As of May 22, 2022, more than two and a half years later, work is now more than 1/5 complete at 21.6%.19 Part of contract that is creating interchange at Thurman Road already under construction along with another interchange with Glen Burnie Road.)
Map of Project Corridor:20
Second is Thurman Road to Havelock Bypass (R-5777C, 8.6 Miles) including construction of service roads. The Letting date for the contract was delayed in February 2020 from June to November 2020 due to design issues and was then put on hold due to funding issues. According to the new 12-month STIP project listing posted in July 2022, the project will be let as a Design-Build contract on January 17, 2023, delayed from August 16, 2022. This probably means start of construction may begin in later in 2023.21
There was also a project to create the Slocum Gate Interchange at Cherry Point MCAS - Completed in March 2020.
Visit NCDOT's US 70 Improvements in James City website.
Segment 7 (Updated 6/23/22)
US 70 Havelock Bypass
Road Type: Unbuilt Freeway Length: 10.1 Miles
Status: Construction Started on August 30, 2019. Project to be completed in May 2024.
NCDOT Project Map:23
On August 1, 2019, NCDOT awarded the $167.2 million contract to build the Bypass to Balfour Beatty Infrastructure, Inc. of Wilmington, NC. Work started on August 30 and as of May 22, 2022 work was nearly 1/2 complete at 47.2%. The current completion date is May 13, 2024.24
Visit NCDOT's Havelock Bypass Project Website.
Segment 8
US 70 from end of Havelock Bypass to Morehead City
Road Type: Mostly 4-lane divided Length: Approx. 11 Miles
Status: Need Upgrade to Interstate Freeway
One project, rebuilding the Newport River Bridge from a 2-lane to 4-lane structure is to start in 2022. Map showing location:25
Remaining projects between the Havelock Bypass and the bridge are not funded. Some doubt I-42 will make it to the bridge due to the difficulty in constructing an interstate through an urban area.
Visit the Future I-42 Exit List
Photos
Link to Photos taken along the I-42 Corridor by AARoads Forum Member Cowboy Wilhelm in May 2022.
Segment 1
(Taken of Future I-42 signs in March 2017)
Begin I-42 sign at the start of the East US 70 Clayton Bypass.
The End Future I-42 sign is after the (Entering) Wake County sign at the western end of the US 70 Clayton Bypass.
Will this cause any confusion? The first exit on Future I-42/US 70 East is for NC 42 in Clayton.
Segment 2
Taken at the Wilson Mills Road intersection by David Johnson on April 17, 2022:
Bridge being constructed as seen from US 70 West.
Google Maps Street View images taken in September and October 2021:
Heading west toward Wilson Mills Road on US 70, clearing for future interchange underway.
The section between Wilson Mills Road and Swift Creek Road has been repaved, shoulder are not interstate standard yet, but clearing to the right of the shoulder would allow for quick further widening in the future.
The current intersection between US 70 West and Swift Creek Road, little construction can be seen at the other future interchange site.
Segment 3
Here are some Google Maps Street View images traveling west along the US 70 Bypass taken in the summer and fall of 2021:
A Future I-42 sign near the start of the Bypass.
The 1 Mile advance sign for the Parktown Road exit, will the exit numbers be changed when I-42 is signed?
The 1/2 Mile advance sign for the US 13 exit, notice Street View already has this part of the Bypass listed as I-42.
The gore sign for the US 13 exit off of the Bypass.
The 1 Mile advance sign for the Wayne Memorial Drive exit.
A combination green auxiliary and blue Hospital Services sign for the Wayne Memorial Drive exit, still on "I-42."
The 1 Mile advance sign for the US 117 exit, behind a Mile 357.5 marker that will be changed when it becomes I-42.
A post-interchange distance sign prior to the US 117 exit, showing the near 20 mile distance US 70 will have to be upgraded between the end of the Goldsboro Bypass and I-95.
The overhead sign for the US 117 exit shares its cantilever support with the 1 mile advance for I-795.
The overhead exit sign for the I-795 North exit, the first ramp of the soon meeting between 2 interstates.
The ground mounted exit sign for the I-795 South exit, eventually that interstate to end at I-40.
The 1 Mile advance sign for the NC 581 exit.
The future temporary end of I-42 West at the merge with US 70 West at the end of the Goldsboro Bypass. Heading east...
The 1/2 Mile advance sign for the US 70 East exit at the start of the Future I-42 Goldsboro Bypass.
Segment 5
(Taken by Adam Prince in July 2021)
One of the several Future I-42 signs placed along US 70 at county lines, here crossing into Craven County, to the right of the now interstate standard right shoulder headed east.
View of Interstate standard shoulders now completed along US 70 in Craven County.
Exit sign for NC 41 near Cove City, next to now interstate standard right shoulder, currently no exit number.
The sign for the next exit for SR 1224, besides the interstate standard right shoulder.
The sign for Craven Community College exit, also still without exit number.
The 3/4 mile advance for what will be the last exit sign without a number, Business 70, the blank space for US 17 South.
The exit sign for the Clarks Road exit, with exit number, next to the widened right shoulder of Future I-42 East.
The overhead exit sign for the NC 43 exit on US 17 North/US 70 East approaching New Bern.
Overhead signage for the East Front Street exit on US 17 North/US 70 East over the water in New Bern.
Exit signage for US 17, on its way north to eventually becoming part of Future I-87 and NC 55 East, notice that all the exit numbers in the New Bern area currently overlap those listed for the Havelock Bypass (see sign plans below), hopefully this will be corrected before that highway opens.
Want to contribute photos for this site? Feel free to email me at rmalme7374 at gmail.com.
Sign Plans
Exit sign plans for Havelock Bypass (unknown why numbers nearly duplicate existing numbers near New Bern):22
Here's an I-42 Shirt advertised on the Internet (no endorsement):
Notes
*Project funding has been suspended by NCDOT due to agency's budget issues. NCDOT is working with state legislature to find alternative sources of revenue. It is unknown when, or if, construction will be started on this project.
1. NCDOT. Future I-36 Corridor Map. Downloaded from: https://connect.ncdot.gov/resources/safety/Route%20Changes/I-42%20Proposed%20Corridor%20Map%20160308.pdf, July 8.
2. WITN. 2020. "Work underway for I-42 from Morehead City to Raleigh." Downloaded from: https://www.witn.com/content/news/-Work-underway-for-I-42-from-Morehead-City-to-Raleigh-567281991.html, Feb. 6.
3. NCDOT. 2022. "Interstate 42 Coming to Eastern N.C. Corridor." Press Release. March 16. Downloaded from: https://www.ncdot.gov/news/press-releases/Pages/2022/2022-03-16-i-42-coming-us-70-corridor.aspx, March 16.
4. NCDOT. 2022. Construction Progress Report, Contract C204359, TIP No. W-5600. Information as of February 22. Downloaded from: https://apps.ncdot.gov/traffictravel/progloc/ProgLocSearch.aspx, March 2.
5. Bolejack, Scott. 2020. Change Coming Soon to US 70. Johnstonian News. March 2. Downloaded from: http://www.johnstoniannews.com/stories/change-coming-soon-to-us-70,202776, March 7.
6. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 4. April, p. 2. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-4.pdf, July 10.
7. NCDOT. 2021. Signing Plans, Part 2. Contract C204359. January 16. Downloaded from: https://xfer.services.ncdot.gov/dsplan/2021%20Highway%20Letting/03-16-21/Plans%20and%20Proposals/Johnston%20C204359/Standard%20PDF%20Files/, Jan. 23, 2021.
8. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 4. April, p. 4. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-4.pdf, July 10.
9. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 4. April, p. 6. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-4.pdf, July 10.
10. NCDOT. Construction Plans. Contract C204333. Location: US 70 (Future I-42) from SR 1003 (Buffalo Road) to Wayne County Line, pp. 2 and 5. Downloaded from: https://xfer.services.ncdot.gov/dsplan/2019%20Highway%20Letting/05-21-19/Plans%20and%20Proposals/JOHNSTON_I-6044_4799.3.1_C204333/Sketch%20Map.pdf, August.
11. US 70 Corridor Commission. 2019. Director's Update. January/February, p. 4. Downloaded from: http://www.super70corridor.com/wp-content/uploads/Jan_Feb_2019-Directors-Report.pdf, July 10.
12. Dunlop, Jim. 2021. Posting on AARoads Forum, Southeast Region, October 8. Downloaded from: https://www.aaroads.com/forum/index.php?topic=19189.425, October 9.
13. AASHTO. 2022. Special Committee on US Route Numbering, 2021 Fall Meeting Final Report, p. 3/5. Downloaded from: https://route.transportation.org/wp-content/uploads/sites/50/2022/02/Final-Report-USRN-Application-Results-Fall-2021.pdf, Feb. 14, 2022.
14. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 2. April, p. 6. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-2.pdf, July 10.
15. NCDOT. 2020. "Route Selected for Future Kinston Bypass." Press Release. February 20. Downloaded from: https://www.ncdot.gov/news/press-releases/Pages/2020/2020-02-20-kinston-bypass-route-selected.aspx, February 20.
16. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 2. April, p. 7. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-2.pdf, July 10.
17. NCDOT. 2019. Five Miles of Craven County Highway to be Upgraded. Press Release. September 25. Downloaded from: https://www.ncdot.gov/news/press-releases/Pages/2019/2019-09-25-craven-county-highway-upgrade-contract.aspx, September 27.
18. NCDOT. 2022. Construction Progress Report, Contract No. C 204225, TIP Nos. R-5777A, R-5777B, U-5713. Information as of November 22. Downloaded from: https://apps.ncdot.gov/traffictravel/progloc/ProgLocSearch.aspx, March 2.
19. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 2. April, p. 9. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-2.pdf, July 10.
20. NCDOT. 2020. Report of Changes to February 2020 12-Month Letting List, p. 3 of 3. Downloaded from: https://connect.ncdot.gov/letting/12%20Month%20Tentative%20Letting%20Library/FEBRUARY%202020%20CHANGES%20REPORT.pdf, February 29.
21. NCDOT. 2022. 12 Month Let List, August 2022-July 2023, p. 47. Downloaded from: https://connect.ncdot.gov/letting/12%20Month%20Tentative%20Letting%20Library/12%20MONTH%20LET%20LIST%20(AUGUST%202022%20-%20JULY%202023).pdf, Aug. 4, 2022.
22. NCDOT. 2019. US 70 Havelock Bypass Project Page. Downloaded from: https://www.ncdot.gov/projects/us-70-havelock-bypass/Pages/default.aspx, July 8.
23. NCDOT. 2022. Construction Project Report, Contract No. C 204177, TIP No. R-1015. Information as of November 16. Downloaded from: https://apps.ncdot.gov/traffictravel/progloc/ProgLocSearch.aspx, March 2.
24. NCDOT. 2019. NC Board of Transportation, US 70 Work Group, US 70 Corridor Workshop, Division 2. April, p. 19. Downloaded from: http://www.super70corridor.com/wp-content/uploads/April-2019-US-70-Workshop-Division-2.pdf, July 10.
25. Plans from: Signing Plan, Craven and Carteret Counties, Location: US 70 Havelock Bypass from South of Carteret/Craven County Line to South of SR 1176 (Carolina Pines Blvd.), NCDOT TIP R-1015, November 20, 2018. Available at: https://xfer.services.ncdot.gov/dsplan/2019%20Highway%20Letting/02-19-19/Plans%20and%20Proposals/Craven_R-1015_C204177/Standard%20PDF%20Files/250%20Signing%20Plans.pdf
Site created: July 10, 2019
Site Updated: May 8, 2022
(c) Robert H. Malme 2022
Return to
Future NC Interstates
Source: https://www.malmeroads.net/ncfutints/fut42.html